Building Progress Update
The building project is taking shape. The steel skeleton for the new Worship Center is done with the next step being the roof installation, followed by siding. Stud walls have been constructed for the Youth addition. Framing is now complete on the Children’s addition with the next steps being to install the metal roof, brick the outside, and doors and windows. Also, additional chairs have been ordered for the Worship Center, taking our number of seats to 300. Exciting times for the Fountain!