Progress Continues!
In photo #1, you can see that the roof for the new worship center is now complete. Work has been started to build the firewall (a concrete wall) between the worship center and the existing building. The second phase of rough-ins for plumbing and electrical is underway. The concrete floor for the worship center will be poured within about a week. Installation of siding for the worship center will start in about two weeks.
In the second picture, you can see that the plywood roofing (and cover) has been completed on for the new youth addition. In the third picture, you can see that the foundation has been laid for the new entrance to the new worship center. The slab will soon be poured for the new entrance.
All in God's timing! Praise Him!