There will be an important update on the building construction project at church on Sunday, August 9th. We will share what is complete, what is left to do, where the project is financially, what you can do to help, and what prayers are needed. In the meantime, this week's update: Drywall and insulation are being installed in the youth and kid's areas this week. There is a good possibility that the roofing on the new main entrance will be done this week. Electrical work is continuing in the worship center, and drywall in the worship center should be complete in the next couple of weeks. The remodel of existing space has started with demolition in the kid's area. Stay tuned for more updates!