Flooring is completed within the administration and kids areas, lobby, and restrooms. The "cloud" is now hung in the lobby (to distribute sound). Painting is underway with most walls having at least the first coat applied. There are many details to finish including painting, lighting, electrical, etc., but we are getting very close! See the updates below:
North view of new lobby - directional lettering will be applied to dark blue walls
A view from the old entrance
A view from the entrance of the new lobby toward the old main entrance
Women's restroom tile
Men's restroom tile