See the Latest Progress on the Remodel
Flooring is completed within the administration and kids areas, lobby, and restrooms. The "cloud" is now hung in the lobby (to distribute sound). Painting is underway with most walls having at least the first coat applied. There are many details to finish including painting, lighting, electrical, etc., but we are getting very close! See the updates below: